Milestones

 

2004

2004 Sakarya MDF facilities were commissioned and production started.

 

2005 January

2005 January Sakarya 1st coating plant was commissioned.

 
 

2005 February

2005 February Production commenced in Sakarya laminate flooring facilities

2006

2006 Sakarya impregnation facilities began production.

 
 

2007

Sakarya 2nd coating plant was commissioned.

2007 February

2007 February Production started in Sakarya 2nd laminate flooring facilities.

 
 

2012

2012 Chemical, 3rd laminate flooring, 3rd coating and 2nd impregnation facilities investment started.


2013

Chemical, 3rd laminate flooring, 3rd coating and 2nd impregnation facilities were commissioned and production started.

 
 

2015

2015 Investment of 2nd MDF, 4th laminate flooring and 4th coating facilities started.

2016

 2016 2nd MDF, 4th laminate flooring and 4th coating facilities were commissioned and production started.